As of 16 Nov 2026, TNERC Tariff Order No. 6 of 2025 (in force since 1 July 2025) still sets business tariffs in Tamil Nadu: ₹10.45 a unit for shops and offices (LT-V), ₹8.25 for small factories (LT-IIIB) and ₹7.50 plus ₹608 per kVA for HT factories. The same rates apply in Chennai and across the state. Unlike homes, businesses get no free units and pay a fixed charge every month.
Fig 01 · What one unit costs a business
Solar cost is before interest. Rooftop plants also pay a network charge of ₹0.80–1.60 on each unit generated.
TNEB commercial and industrial unit rates 2026 (LT-V, LT-IIIB, HT)
| Connection | Energy charge | Fixed / demand charge (a month) |
|---|---|---|
| LT-V (Tariff V) shops, offices and private clinics | ₹10.45 on every unit once you cross 100 units a bill (₹6.65 below) | ₹110 a kW up to 50 kW · ₹332 to 112 kW · ₹608 above* |
| LT-IIIB (3B) small and medium factories | ₹8.25 | ₹84 a kW up to 50 kW · ₹165 to 112 kW · ₹608 above |
| HT-I HT factories and IT services | ₹7.50 | ₹608 per kVA |
| HT-III malls, hotels, private hospitals | ₹9.40 | ₹608 per kVA |
*Fixed charges are billed per kW (or part) of contracted demand. The tariff order does not spell out whether a higher band rate applies to the whole load or only to the kW inside that band, so check your bill if you are above 50 kW. Electricity tax is extra. For July 2025 to June 2026 the state also paid part of the bill for small users (LT-V up to 500 units a bill paid ₹6.45 / ₹10.15; LT-IIIB up to 50 kW paid ₹8.00 plus ₹81 a kW). TNERC Order No. 4 of 2026 funded that support only up to 30 June 2026, so check your latest bill for the rate you are charged.
What a month costs
| Business | Units a month | Energy | Fixed | Solar that fits | Saves in year 1 |
|---|---|---|---|---|---|
| Shop (LT-V, 30 kW load) | 3,000 | ₹31,350 | ₹3,300 | 19 kW | ₹2.28 lakh |
| Small factory (LT-IIIB, 45 kW) | 10,000 | ₹82,500 | ₹3,780 | 45 kW | ₹4.56 lakh |
| HT factory (300 kVA) | 1,00,000 | ₹7,50,000 | ₹1,82,400 | 300 kW | ₹26.1 lakh |
Solar sizes and savings come from our bill calculator. They count the network charge, upkeep and panel ageing, keep the plant within your sanctioned load (net billing allows no more), and leave out the 40% depreciation benefit, which improves the return further.
Fig 02 · A business day on the TNEB clock
Applies to most HT connections and to LT-IIB, LT-IIIB and LT-V. LT meters that do not record time of day are charged as if 20% of units were used at peak (about +5% overall). For FY 2026-27 (to 31 Mar 2027), LT-IIIB factories pay 15% with a smart meter and nothing without one; the state covers the rest.
Where solar fits
- Size it to your daytime load, not your roof. Units you use save ₹6–9 each; extra units sent to the grid earn only ₹3.10–3.61 (why).
- Solar cuts the energy charge, not the fixed charge. See fixed and demand charges.
- No subsidy for businesses, but tax and loan benefits help: what you get instead.
Not sure which tariff you are on? WhatsApp us your EB bill; we will read it for you.
Frequently asked questions
What is the TNEB commercial tariff per unit in 2026?
Shops and offices (LT-V) pay ₹10.45 on every unit once they use more than 100 units in a two-month bill, and ₹6.65 a unit below that, under TNERC Tariff Order No. 6 of 2025. A fixed charge of ₹110 a kW a month (up to 50 kW) and electricity tax are added.
What is tariff 5 in TNEB?
Tariff V (LT-V) is the low-tension commercial tariff for shops, offices and private clinics. It is ₹6.65 a unit up to 100 units a bill and ₹10.45 on every unit above that, plus a fixed charge from ₹110 a kW a month.
What is the current unit price for a shop (kadai) in Tamil Nadu?
₹10.45 a unit for a shop using more than 100 units in a two-month bill, the same in Chennai and the rest of Tamil Nadu. A very small shop using 100 units or less pays ₹6.65 a unit.
What is the TNEB 3B tariff per unit?
LT-IIIB (3B), for small and medium factories, is ₹8.25 a unit, plus a fixed charge of ₹84 a kW a month up to 50 kW, ₹165 from 50 to 112 kW and ₹608 above 112 kW.
What is the HT maximum demand charge in TNEB?
₹608 per kVA a month, billed on the higher of your recorded maximum demand or 90% of your contract demand (the same rule for every HT connection). HT-I industries pay ₹7.50 a unit on top; HT-III commercial pays ₹9.40.
What are the TNEB peak hours for industries?
6–10 am and 6–10 pm, when the energy charge is 25% higher; 10 pm–5 am is 5% cheaper. It applies to most HT connections and to LT-IIB, LT-IIIB and LT-V. For FY 2026-27, LT-IIIB factories pay 15% with a smart meter and nothing without one.
Sources: TNERC Tariff Order No. 6 of 2025 (in force from 1 July 2025; no new tariff in 2026), TNERC Order No. 4 of 2026 (state support), TNERC GISS Regulations 2021. Checked 16 Nov 2026.